This construction project covers 23 km of the tunnel toward Modane.
Construction site photos
Key data
23 km
of base tunnel excavated
3
TBMs
65
months of works
625
people employed
Companies involved in the works
TELT awarded a €1.43 billion contract to a consortium composed of VINCI Construction Grands Projets (lead contractor), Dodin Campenon Bernard, VINCI Construction France TP Lyon and Webuild. Project management is being carried out by a consortium led by Setec, together with Systra, Italferr and Pini Group.
Project progress
68%
Completed works
All construction updates